krsuper2
Chris's build site for the
construction
CURRENTLY WORKING ON
Fuselage

TOTAL AIRCRAFT BUILD TIME
750.42 Hours

PROGRESS CHARTS







DETAILED PROGRESS

Empennage 376.5 Hours
Fuselage 306.28 Hours
Wing 50.5 Hours
Shop Supplies 2 Hours
Miscellaneous 13.6 Hours
Tools 1.01 Hours
Diversion time 0.5 Hours
Canopy 0.03 Hours


last update
SITE WAS UPDATED ON
Monday, May 31, 2010

contact 
SEND AN EMAIL
Chris @ digflying.com

specs 
WHAT MAKES IT TICK
Length                   19'
Wing Span             24'
Total Wing Area     93 ft^2
Empty Weight         750
Gross Weight        1200
Useful Load           450
Fuel Cap                26 gal
Stall Speed            48 mph
Maximum Speed    170 mph
Cruise Speed        140 mph
Range                    600 miles
Engine                   Corvair 2700
Power                   100 HP
Power Loading     12 lbs/hp
Wing loading         12.5 lbs/sq ft
Fuel consumption  5.5 gph
Seating                  2 across
Gear                      Tri-Gear
Cabin Width           43"

disclaimer
THE LEGALESE
This website was built to document my work on my KRSuper2 in compliance with the FAA requirements needed to certify my aircraft. My experiences and comments are by no means to be considered as instructions on how to build a KRSuper2 or any other aircraft.

A Modern take on a classic aircraft with an all composite design


If you would like to help Project Gemini get off the ground, please click the donation button below. THANKS!

Or Email us if you have an engine to donate or if you would like to sponsor us. THANKS!

BUILD SITE OF A KRSUPER2

The KRSuper2 is an all composite aircraft with the design influenced by the Rand-Robinson KR2.  It is the brainchild of Scott Watts and is thoroughly documented on his site!




A special thanks to Scott for making this design available!   Check out the website, and monitor his progress.
KRSUPER2 TWINS Castor (Chris) and Pollux (Paul)

A friend of mine is also simultaneously building a KRSuper2

The logo is inspired by the NASA Gemini patch from the 1965 and 1966 missions
WHAT'S BEEN DONE LATELY

As of  Monday, May 31, 2010 

2.5 Hours
Summary: Turtle deck

Details: Laid out the foam for the turtle deck and micro'd the pieces together.









welcome
Project Gemini
the latest progress